Tiu Suico vs Simeon Habana, G.R. No. L-21106, February 21, 1924
Subject: Obligations and Contracts
FACTS
Habana engaged
Suico to construct a building for him. In the process of the construction, many
written alterations were agreed upon and really made, but it was proved that
essentially, the plans followed were the original plans. It must be stated that
in the contract, a specific amount for the construction was agreed upon. Later,
when the building was finished, the contractor wanted to abandon the original
price on the ground that the alterations in the building had caused an
abandonment or a novation of the old contract. The contractor therefore wanted
to be paid, not on the basis of the contract, but on the basis of quantum
meruit. The owner did not consent to this.
ISSUE
Whether or not there was
novation.
RULING
No, there was no novation here.
Under Art. 1724 of
the New Civil Code, the contractor cannot demand an increase in the price
unless the change in the plans and specifications was authorized in writing and
the additional price to be paid was also determined in writing by both parties.
In this case, the
old contract was not abandoned since, after all, the original plans were
followed. Therefore, without the consent of the owner, the contractor cannot
treat the old contract as abandoned. The contractor, without the consent of the
owner, cannot recover on the basis of quantum meruit (on the work done).
Rather, the contract price will form the basis for payment, plus the cost of
the alterations.
No comments:
Post a Comment