Lorenzo Shipping v. BJ
Marthel, 443 SCRA 163, G.R. No. 145483, November 19, 2004
Subject: Obligations and
Contracts
FACTS
Petitioner Lorenzo Shipping
Corporation is a domestic corporation engaged in coastwise shipping. It used to
own the cargo vessel M/V Dadiangas Express. The respondent BJ Marthel
International, Inc. is a business entity engaged in trading, marketing, and
selling of various industrial commodities. It is also an importer and
distributor of different brands of engines and spare parts.
In 1989, petitioner asked
respondent for a quotation for various machine parts.
Petitioner issued a two
separate Purchase Orders. Instead of paying the 25% down payment for the first
cylinder liner, petitioner issued in favor of respondent ten postdated checks
to be drawn against the former's account with Allied Banking Corporation. The
checks were supposed to represent the full payment of the first cylinder liner
while the liner was subject to term of payment to be "25% upon delivery,
balance payable in 5 bi-monthly equal installments." Both purchase orders
did not state the date of the cylinder liner's delivery.
In January 1990, respondent
deposited petitioner's check that was postdated 18 January 1990, however, the
same was dishonored by the drawee bank due to insufficiency of funds.
Petitioner claimed that it replaced said check with a good one, the proceeds of
which were applied to its other obligation to respondent. For its part,
respondent insisted that it returned said postdated check to petitioner.
Respondent thereafter placed
the order for the two (02) cylinder liners with its principal in Japan, Daiei
Sangyo Co. Ltd., and delivered the two (02) cylinder liners at petitioner's
warehouse in North Harbor, Manila. The sales invoices evidencing the delivery
of the cylinder liners both contain the notation "subject to verification"
under which the signature of Eric Go, petitioner's warehouseman, appeared.
Respondent thereafter sent a
Statement of Account to petitioner. While the other items listed in said
statement of account were fully paid by petitioner, the two-cylinder liners delivered
to petitioner on 20 April 1990 remained unsettled. Consequently, respondent
sent a demand letter to petitioner requiring the latter to pay the value of the
cylinder liners subjects of this case. Instead of heeding the demand of
respondent for the full payment of the value of the cylinder liners, petitioner
sent the former a letter dated 12 March 1991 offering to pay only P150,000 for
the cylinder liners. In said letter, petitioner claimed that as the cylinder
liners were delivered late and due to the scrapping of the M/V Dadiangas
Express, it (petitioner) would have to sell the cylinder liners in Singapore
and pay the balance from the proceeds of said sale.
Due to the failure of the
parties to settle the matter, respondent filed an action for sum of money and
damages before RTC of Makati City.
Petitioner alleged that time
was of the essence in the delivery of the cylinder liners and that the delivery
on 20 April 1990 of said items was late as respondent committed to deliver said
items "within two (2) months after receipt of firm order" from
petitioner.
RTC dismissed the action upon
findings that respondent bound to the quotation it submitted to petitioner
particularly with respect to the terms of payment and delivery of the cylinder
liners. It also declared that respondent had agreed to the cancellation of the
contract of sale when it returned the postdated checks issued by petitioner.
Aggrieved, respondent filed an
appeal with the CA which reversed and set aside RTC’s decision. The appellate
court brushed aside petitioner's claim that time was of the essence in the
contract of sale between the parties herein considering the fact that a
significant period of time had lapsed between respondent's offer and the
issuance by petitioner of its purchase orders. There was no evidence of the
alleged cancellation of orders by petitioner and that the delivery of the
cylinder liners on 20 April 1990 was reasonable under the circumstances.
Petitioner insists that
although its purchase orders did not specify the dates when the cylinder liners
were supposed to be delivered, nevertheless, respondent should abide by the
term of delivery appearing on the quotation it submitted to petitioner.
Petitioner theorizes that the quotation embodied the offer from respondent while
the purchase order represented its (petitioner's) acceptance of the proposed
terms of the contract of sale. Thus, petitioner is of the view that these two
documents "cannot be taken separately as if there were two distinct
contracts."
Hence this petition.
ISSUE
Whether or not there was late
delivery of the subjects of the contract of sale to justify petitioner to
disregard the terms of the contract considering that time was of the essence
thereof.
RULING
No, there was late delivery.
Under the law, the power to
rescind obligations is implied in reciprocal ones, in case one of the obligors
should not comply with what is incumbent upon him.
In this case, there is no
showing that petitioner notified respondent of its intention to rescind the
contract of sale between them. Quite the contrary, respondent's act of
proceeding with the opening of an irrevocable letter of credit on 23 February
1990 belies petitioner's claim that it notified respondent of the cancellation
of the contract of sale. Truly, no prudent businessman would pursue such action
knowing that the contract of sale, for which the letter of credit was opened,
was already rescinded by the other party.
No comments:
Post a Comment